Drastic measures needed to realize disbursement target of public funds

As the disbursed amount between January and August was equivalent to 50.7% of the target, the government is under pressure to spend the remaining 50% in the remaining four months.

Despite improvements in disbursement of public funds, the progress remains slower than expected and requires huge efforts to meet the government target by year-end.

 Drastic measurse are required for Vietnam to realize the disbursement target of public funds this year. Photo: Thanh Hai. 

 

In the first eight months of 2020, the disbursed amount of public investment stood at VND250 trillion (US$10.8 billion), up 30.4% year-on-year but equivalent to only 50.7% of the target.

 

The government, therefore, is under pressure to expend the remaining 50% of public investment funds in the remaining four months.

 

As of present, the disbursement progress lies on the implementation of major infrastructure projects, including the Eastern North-South expressway project, Long Thanh International Airport, or the upgrade of runways of international airports of Tan Son Nhat and Noi Bai, among others.

 

Meanwhile, projects financed by the official development assistance (ODA) fund such as the Ben Luc – Long Thanh expressway and urban railways are lagging behind schedule, resulting in a low disbursement rate.

 

Minister of Planning and Investment Nguyen Chi Dung attributed the slow disbursement to changes in policies, difficulties in site clearance, as well as lack of capabilities from project owners and contractors.

 

Regarding ODA projects, Mr. Dung said many are lacking legal grounds to start construction works, mainly due to adjustments to the financing agreements and investment procedures.

 

Mr. Dung added the Covid-19 pandemic has also impacted foreign-invested projects, specifically in importing equipment, machinery, and the entry of foreign experts.

 

Amid mounting difficulties, Prime Minister Nguyen Xuan Phuc has reiterated the government’s determination to fully disburse entirely the target amount of public funds, adding this is key to boost economic growth during the Covid-19 crisis.

 

In a meeting late August, Mr. Phuc warned officials would face disciplinary actions if their ministries and localities fail to realize their respective disbursement targets of public investment funds for this year,

 

On this issue, Minister of Planning and Investment Dung also said the government is willing to transfer state capital from projects whose disbursement is lagging behind those with faster pace.

 

Among measures to boost the disbursement performance, Mr. Dung said both central and local governments would hold monthly meetings to address related issues.

 

In a meeting with the ADB’s Country Director to Vietnam Andrew Jeffries on September 17, PM Phuc requested the bank’s support in disbursing US$900 million to ADB-funded projects in 2020.

Đọc nhiều
HỎI ĐÁP THÔNG MINH

BÌNH LUẬN (0)

Đừng bỏ lỡ
Tin mới
Đường sắt đô thị: xương sống “xanh” của giao thông đô thị

Đường sắt đô thị: xương sống “xanh” của giao thông đô thị

28/01/2025 | 10:56

Kinhtedothi - Đường sắt đô thị (ĐSĐT) được ví như xương sống của hệ thống giao thông công cộng bởi năng lực vận chuyển ưu việt. Hơn nữa, ĐSĐT còn là phương tiện chủ đạo để những đô thị lớn như Hà Nội kiến tạo một hệ thống giao thông xanh, bến vững.

Hà Nội: tăng cường xử phạt vi phạm trông giữ xe

Hà Nội: tăng cường xử phạt vi phạm trông giữ xe

28/01/2025 | 10:51

Kinhtedothi - Thanh tra Sở GTVT Hà Nội cho biết, năm 2024 đã xử phạt hơn 748 trường hợp vi phạm trông giữ xe, phạt tiền hơn 3,4 tỷ đồng. Năm 2025, đơn vị sẽ tiếp tục phối hợp với lực lượng liên ngành cùng địa phương tăng cường kiểm tra các điểm trông giữ xe trên địa bàn TP.

“Tết vội” trên công trường trọng điểm của Thủ đô Hà Nội

“Tết vội” trên công trường trọng điểm của Thủ đô Hà Nội

27/01/2025 | 08:34

Kinhtedothi - Những ngày sát Tết Nguyên đán Ất Tỵ, trên công trường khoan hầm tuyến đường sắt đô thị Nhổn - Ga Hà Nội vẫn nhộn nhịp công nhân, kỹ sư cùng máy móc ầm ì hoạt động. Để bảo đảm “đường găng” tiến độ, công trường sẽ nghỉ Tết muộn và quay trở lại làm việc từ sớm.

Bổ sung quy định mới giúp khắc phục bất cập đầu tư trạm dừng nghỉ

Bổ sung quy định mới giúp khắc phục bất cập đầu tư trạm dừng nghỉ

25/01/2025 | 07:30

Kinhtedothi - Do các quy định ở giai đoạn trước về đầu tư, kinh doanh, khai thác trạm dừng nghỉ chưa đầy đủ, rõ ràng, nên việc triển khai xã hội hóa nguồn lực gặp rất nhiều khó khăn. Từ ngày 1/1/2025, Nghị định 165/2024/NĐ-CP có hiệu lực sẽ giúp khai thông cơ chế, tháo gỡ các bất cập.

Tin tài trợ