Hanoi expected to realize disbursement target of ODA funds in 2020

Hanoi has set up six task force teams specialized in accelerating disbursement of public funds.

As of October 28, Hanoi has disbursed VND1.81 trillion (US$78.2 million) of the official development assistance (ODA) fund, or 51.97% of the target and targets to realize the full amount allocated for this year, according to Vice Chairman of the Hanoi People’s Committee Nguyen Doan Toan.

 Overview of the online conference from Hanoi People's Committee. 

 

In 2020, the government allocated VND5.23 trillion (US$226 million) for nine ODA projects in Hanoi, for which the city’s leaders have instructed local authorities to work on measures to avoid any disruption to ODA-funded projects despite severe impacts of the Covid-19 pandemic, stated Mr. Toan at an online government meeting on October 29.

 

Among measures to speed up the disbursement of ODA funds, the municipal People’s Committee urged related departments and units to complete investment procedures for kicking off new projects, as well as pushing for speedier site clearance, Mr. Toan continued.

 

Additionally, Hanoi’s leaders have been active in addressing concerns of contractors related to project implementation right in early 2020, he noted.

 

On September 30, the Hanoi People’s Committee issued decision No.4402/QD-UBND on the establishment of six task force teams specialized in accelerating disbursement of public funds.

 

According to Mr. Toan, these teams have basically resolved all issues related to the construction process, except for the Urban railway project No.2, section Nam Thang Long – Tran Hung Dao, which has a problem related to the adjustment of investment capital; and the planning of the subway Station C9 near Hoan Kiem lake.

 

In the coming time, Mr. Toan suggested the central government continue supporting the city in attracting ODA funds for infrastructure development, especially in transportation to help boost connectivity with other provinces and cities; water supply and waste water treatment projects; and urban railway projects.

 Prime Minister Nguyen Xuan Phuc at the meeting. Source: VGP. 

 

Disbursement of public funds remains key priority

 

At the meeting, Prime Minister Nguyen Xuan Phuc said the challenges remains huge as nearly VND41 trillion (US$1.77 billion) in ODA funds, or 70% of the total, needs to be fully disbursed in the remaining two months of the year.

 

Mr. Phuc urged all localities and government agencies to continue pushing for speedier disbursement of public funds, which stood at 60% in the first nine months of the year.

 

The Vietnam PM said ODA is an important source for economic development, especially as the country is in need of investment capital for socio-economic development.

 

Mr. Phuc requested leaders of provinces/cities and government agencies to take greater responsibility in ensuring the full disbursement of public funds in the coming months, saying those with poor competence or responsibility in this task would be replaced.

 

Mr. Phuc expected government agencies to simplify the administrative procedures in the approval process of investment projects, while the Ministry of Planning and Investment is tasked with reporting to the Prime Minister on a monthly basis on the transferring of ODA funds from projects with slow disbursement progress to those with faster pace.

Đọc nhiều
HỎI ĐÁP THÔNG MINH

BÌNH LUẬN (0)

Đừng bỏ lỡ
Tin mới
Đường sắt đô thị: xương sống “xanh” của giao thông đô thị

Đường sắt đô thị: xương sống “xanh” của giao thông đô thị

28/01/2025 | 10:56

Kinhtedothi - Đường sắt đô thị (ĐSĐT) được ví như xương sống của hệ thống giao thông công cộng bởi năng lực vận chuyển ưu việt. Hơn nữa, ĐSĐT còn là phương tiện chủ đạo để những đô thị lớn như Hà Nội kiến tạo một hệ thống giao thông xanh, bến vững.

Hà Nội: tăng cường xử phạt vi phạm trông giữ xe

Hà Nội: tăng cường xử phạt vi phạm trông giữ xe

28/01/2025 | 10:51

Kinhtedothi - Thanh tra Sở GTVT Hà Nội cho biết, năm 2024 đã xử phạt hơn 748 trường hợp vi phạm trông giữ xe, phạt tiền hơn 3,4 tỷ đồng. Năm 2025, đơn vị sẽ tiếp tục phối hợp với lực lượng liên ngành cùng địa phương tăng cường kiểm tra các điểm trông giữ xe trên địa bàn TP.

“Tết vội” trên công trường trọng điểm của Thủ đô Hà Nội

“Tết vội” trên công trường trọng điểm của Thủ đô Hà Nội

27/01/2025 | 08:34

Kinhtedothi - Những ngày sát Tết Nguyên đán Ất Tỵ, trên công trường khoan hầm tuyến đường sắt đô thị Nhổn - Ga Hà Nội vẫn nhộn nhịp công nhân, kỹ sư cùng máy móc ầm ì hoạt động. Để bảo đảm “đường găng” tiến độ, công trường sẽ nghỉ Tết muộn và quay trở lại làm việc từ sớm.

Bổ sung quy định mới giúp khắc phục bất cập đầu tư trạm dừng nghỉ

Bổ sung quy định mới giúp khắc phục bất cập đầu tư trạm dừng nghỉ

25/01/2025 | 07:30

Kinhtedothi - Do các quy định ở giai đoạn trước về đầu tư, kinh doanh, khai thác trạm dừng nghỉ chưa đầy đủ, rõ ràng, nên việc triển khai xã hội hóa nguồn lực gặp rất nhiều khó khăn. Từ ngày 1/1/2025, Nghị định 165/2024/NĐ-CP có hiệu lực sẽ giúp khai thông cơ chế, tháo gỡ các bất cập.

Tin tài trợ